Skipping tasks
To have a task skipped during synchronisation, you can:
-
Set its issue key custom field (selected in the following combo box of Basic Mappings) to “SKIP”.
Tick the “Do not create issue if no assignee” check box (Project Settings/Basic Mappings) and
-
if the assignee mapping method is “Resource Name ”, leave the “Resource Name” field of the task blank.
-
if the assignee mapping method is "Resource Field ", leave the custom field of the resource empty (Resource Sheet).
-
if the assignee mapping method is "Field", leave the custom field of the task empty.
-