Skipping tasks

To have a task skipped during synchronisation, you can:

  • Set its issue key custom field (selected in the following combo box of Basic Mappings) to “SKIP”.

    SKIP value in the Issue Key field

  • Tick the “Do not create issue if no assignee” check box (Project Settings/Basic Mappings) and

    • if the assignee mapping method is “Resource Name ”, leave the “Resource Name” field of the task blank.

      Skipping tasks when Resource Name is mapped

    • if the assignee mapping method is "Resource Field ", leave the custom field of the resource empty (Resource Sheet).

      Skipping tasks when Resource Field is mapped

    • if the assignee mapping method is "Field", leave the custom field of the task empty.

      Skipping tasks when a custom field is mapped