Question: How can dependencies (predecessors) be synchronised between Jira and Microsoft Project?
Answer: Predecessors in Microsoft Project can be mapped to issue links in Jira (like blocks/blocked by) using the Links mapping in Ceptah Bridge. Please refer to the user guide for detailed instructions on configuring this mapping.
Question: How can MS Project predecessor types (FS, FF, SS, SF) be mapped to Jira issue link types during synchronisation?
Answer: You can map each MS Project predecessor type (FS, FF, SS, SF) to a different Jira issue link type by creating additional mappings as needed.