Linking Existing Jira Issues to MS Project Tasks
Question: How can I link existing Jira issues with MS Project tasks for synchronisation?
Answer: You can link existing Jira issues to MS Project tasks by entering the key of the corresponding issue into the MS Project field mapped to Issue Key (Text10 by default) for each task to be re-connected. This enables synchronisation between pre-existing issue-task pairs.