Importing Jira Components as Tasks
Question: Can I import JIRA components as tasks in MS Project using Ceptah Bridge?
Answer: Ceptah Bridge does not support importing JIRA components as summary tasks in MS Project; components are only imported as field values. To organise tasks by components, you can import issues ordered by component using JQL and manually create component summary tasks in MS Project. You can also automate component grouping with a VBA macro.