To have a task skipped during synchronisation, you can:

  1. Set its issue key custom field (selected in the following combo box of Basic Mappings) to “SKIP”.

  2. Tick the “Do not create issue if no assignee ” check box (Project Settings/Basic Mappings) and

    • if the assignee mapping method is “Resource Name ”, leave the “Resource Name” field of the task blank

    • if the assignee mapping method is "Resource Field ", leave the custom field of the resource empty (Resource Sheet)

    • if the assignee mapping method is "Field ", leave the custom field of the task empty